1. Preparation: Before installation, ensure that the various equipment and components of the organic fertilizer production line have been all in place, and have been inspected and tested to ensure that there is no damage or omission during transportation.

2. Platform preparation: Prepare a smooth and firm installation platform or foundation according to the size and layout requirements of the organic fertilizer equipment. The quality and stability of the platform directly affect the stability and safety of the equipment.

3. Equipment positioning: According to the process flow of the production line and the relationship between the equipment, the position of each equipment is rationally arranged to ensure the connection and convenient operation between the equipment.

4. Installation equipment: According to the installation sequence of equipment, first install large equipment such as fermentation compost machine, mixer, etc., and then install auxiliary equipment such as conveyor, packaging machine, etc. During the installation, pay attention to the levelness and verticality of the device, and use tools such as a level to calibrate the device to ensure device stability.

5. Test and commissioning: After the installation is complete, conduct preliminary test and commissioning of the equipment. Check that each device is operating properly and that the various components and control systems are responding properly. If found problems, timely adjustment and correction.

6. Record and document: During the installation process, record the details and key parameters of each step in a timely manner to form a documentation record of the installation and debugging. These records provide an important reference for future maintenance and upgrades.

In short, the correct installation should be operated in strict accordance with the installation instructions and technical requirements, and ensure that each step meets the safety standards and production requirements, which is the key to ensure the smooth operation of the organic fertilizer production line.